Case Studies

Keeping a mission-critical project on track at commissioning.

The challenge

Turning a potential project setback into a quick, seamless solution.

During late-stage work, the team discovered a need to replace a failed circuit breaker—a component required to proceed safely and complete the project.

At this point in the schedule, delays would be costly. Traditional sourcing options required locating a non-local supplier, placing an order, and waiting for delivery. This put the entire project schedule at risk by potentially impacting downstream trades and the owner’s operational timeline.

The general contractor needed an immediate solution from a partner they trusted to act fast, solve the problem, and keep the project moving.

The solution

The general contractor called Hardin Power Group based on prior experience navigating complex and requirement constrained projects.

Leveraging the team’s deep industry network and reach, the team located the required circuit breaker faster than could be done through standard channels. Within two hours, the circuit breaker was sourced, tested, and on-site—eliminating what could have been a multi-day delay.

Hardin Power Group’s capabilities extended beyond sourcing into execution. As certified riggers, the team safely removed and handled the equipment, brought the right specialists on-site, and operated seamlessly within the general contractor’s workflow.

The Result

This was about more than electrical equipment availability. It was about knowing who to call, where to look, and how to move quickly without compromising safety or quality. The team at Hardin Power Group:

  • Project schedule preserved during a critical pre-commissioning window
  • Avoided non-local sourcing, saving days of shipping delays
  • Increased trust from both the GC and the owner

What began as a potentially disruptive issue became an opportunity to strengthen trust and deliver solutions. The general contractor described the experience as a turning point – one that further solidified Hardin Power Group as a trusted resource for responsiveness, network reach, and performance under pressure.

The project moved forward and Hardin Power Group reinforced its reputation as the go-to partner teams call when there is zero margin for error.

The Result

This was about more than electrical equipment availability. It was about knowing who to call, where to look, and how to move quickly without compromising safety or quality. The team at Hardin Power Group:

  • Project schedule preserved during a critical pre-commissioning window
  • Avoided non-local sourcing, saving days of shipping delays
  • Increased trust from both the GC and the owner

What began as a potentially disruptive issue became an opportunity to strengthen trust and deliver solutions. The general contractor described the experience as a turning point – one that further solidified Hardin Power Group as a trusted resource for responsiveness, network reach, and performance under pressure.

The project moved forward and Hardin Power Group reinforced its reputation as the go-to partner teams call when there is zero margin for error.

The response

“When jobs are challenged, they always come through. They found the circuit breaker before the electrician could, got it on site and tested within two hours, and kept the project moving.”

-Adam Leavitt, General Contractor

Let’s build your success story.

Talk to the Hardin Power Group team about how we can support your next project.